DCM-04C-MOVE
What this test proves
Workstations retrieve studies to themselves.
How it is tested
- Configure the probe's store SCP as a destination in the settings
- C-MOVE the study there
- Pass if completed equals the instance count and the bytes arrive unchanged (licensed), or the move is refused
Results
| Column | Expected | Result | Detail | Time |
|---|---|---|---|---|
| No license | Asks for a license | Pass |
C-MOVE final 0x0124: completed 0, failed 0, warning 0
destination received 0; expected 0
Query/retrieve is switched off: No license key is installed. Ent
|
5 ms |
| Built-in trial | Works | Pending |
Trial: needs an administrator run on a disposable test machine, because the built-in trial writes machine-wide records.
|
|
| PACS Developer | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
59 ms |
| PACS Pro | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
58 ms |
| PACS Enterprise | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
59 ms |
| Router Developer | Refused | Pass |
C-MOVE final 0x0124: completed 0, failed 0, warning 0
destination received 0; expected 9
Query/retrieve is not in your product (PrologicSign Router, Deve
|
5 ms |
| Router Pro | Refused | Pass |
C-MOVE final 0x0124: completed 0, failed 0, warning 0
destination received 0; expected 9
Query/retrieve is not in your product (PrologicSign Router, Pro)
|
4 ms |
| Router Enterprise | Refused | Pass |
C-MOVE final 0x0124: completed 0, failed 0, warning 0
destination received 0; expected 9
Query/retrieve is not in your product (PrologicSign Router, Ente
|
4 ms |
| PACS + Viewer Developer | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
59 ms |
| PACS + Viewer Pro | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
58 ms |
| PACS + Viewer Enterprise | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
59 ms |
| PACS + Router Developer | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
59 ms |
| PACS + Router Pro | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
62 ms |
| PACS + Router Enterprise | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
61 ms |
| PACS + Router + Viewer Developer | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
58 ms |
| PACS + Router + Viewer Pro | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
60 ms |
| PACS + Router + Viewer Enterprise | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
61 ms |
| Expired license | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
60 ms |
| Revoked license | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
61 ms |
| Developer key, renewed | Works | Pass |
C-MOVE final 0x0000: completed 9, failed 0, warning 0
destination received 9; expected 9
|
60 ms |
Test run
- Build
- PrologicSign PACS 0.1.0 ship build (bfd61b5): Release, obfuscated, strong-named
- Run
- ba7cd839-7956-4ab5-8e58-8e1444c7baf4
- Started (UTC)
- 2026-10-28 06:56:57, finished 08:49:12
This report is not complete: see why rows are pending.